Terawatt Scale

Terawatt
Scale

How to build AI data centers that work for industry, communities and the climate.

November 2026
Brook Porter, Jake Tauscher and Julia O'Donnell
→ next   click a panel for more
The pushback

Data centers are unpopular, and it showed in the midterms

1 · Data centers are unpopular
% of Americans who oppose a data center near their home
Aug ’2513%30%15%18%24%42% opposeFeb ’269%18%21%14%37%51% opposeMay ’267%14%9%16%54%70% opposeAug ’264%11%10%14%61%75% oppose
Strongly opposeSomewhat opposeSupport or not sure
2 · The midterm results
56%of voters said it factored in
+7Senate seats flipped
TX · OH · GANew governors back a pause
43 of 44local limits passed
3 · Mapped to gigawatts
All planned383 GWBacks a pause158.6 GW41%Governor backs a pause18%New rules, no pause30%No governor’s race10%Little signalTexas 88.4Ohio 21.9Georgia 20.2New Mexico 11.05 others 17.1
Sources: Heatmap News (Aug 19, 2026); Cleanview (Nov 4, 2026); Gallup (Oct 29, 2026); The Information tally of local measures (Nov 4, 2026); AP and CBS projections; Level39 on Texas permitting (Nov 4, 2026); Evercore ISI and Morgan Stanley (Nov 4, 2026; internal); G2 “Midterms and the AI Trade.” Results unofficial as of Nov 4, 2026. Click the midterms or gigawatts panel for detail; 56% is the NBC exit poll (AI ranked 10th of 11 issues).
Introduction

What industry needs, what communities deserve

Industry

What industry needs

Speed to power
Scale
Uptime
See the largest buildout in history
Communities

What communities deserve

Lower prices
No pollution
Tax revenue
See who is paying
What industry needs

Data centers are already being built at a pace and scale unlike any infrastructure wave in history.

Infrastructure-wave spending as charted in the paper; AI buildout through 2030.
What communities deserve

This boom is being financed by the richest companies in history.

Companies with these resources can afford to build well. There is no financial reason for a community to bear the cost of a data center.

Market value and capex ($ trillions), Oct 2-5, 2026
AI platforms (~$18.4T)Oil majors (~$3.2T)Hyperscaler capex
Market values Oct 2-5, 2026, and hyperscaler capex, as charted in the paper.
Introduction
Click any wave to see its site in detail
Introduction
Wave 1 · Grid connected
Introduction
Wave 2 · Bring your own power · 1 of 5
Introduction
Wave 2 · Bring your own power · 2 of 5
Introduction
Wave 2 · Bring your own power · 3 of 5
Introduction
Wave 2 · Bring your own power · 4 of 5
Introduction
Wave 2 · Bring your own power · 5 of 5
Introduction
Wave 3 · Off-grid, efficient and green
Cheapest and most scalable

Renewables are the cheapest and most scalable form of power

Cheapest new electricity by LCOE

Click to play the animation

Still 5x gas after adjusting for capacity factor

Click to step through
Intermittency

Intermittent renewables cannot serve data centers alone, and firming with li-ion is too expensive

Up-front cost to firm a 1 GW AI campus with solar + Li-ion ($B)
The missing piece: cost-effective long-duration (50–100 hours) storage
Sources: Ember, “24 Hour Solar Electricity” (June 2025): Ember’s solar and battery sizing for Las Vegas, priced at Ember’s 2024 global costs ($388/kW solar, $165/kWh storage, grid connection, inverter, 10% soft costs). Past 99.4% (dotted): G2 extrapolation of Ember’s sizing trend.
Commercializing

Long-duration energy storage is scaling now

Antora installationCommercial scale
Antora↗

Heated carbon blocks

Energy Dome installationCommercial scale
Energy Dome↗

Compressed carbon dioxide

Form Energy installationPilot scale
Form Energy↗

Iron-air batteries

Scorecard

Solar and LDES is the fastest, most scalable, and most cost effective option for data center builders

Click any row or cell for why it scores that way
Climate

This is also the best solution for the climate

US greenhouse gas emissions (Gt CO2e / year)
Sources: Rhodium Group (Jan 13, 2026); G2 estimates. G2 estimates for the 2035 emissions paths, as charted in the paper.
Takeaway

Cost-effective power at speed and scale; climate and community friendly

Industry
Fast, firm, abundant, cost-effective power
Communities
Lower bills, clean air and water, lasting jobs and tax revenue
Climate
Avoiding another 30 years of combustion
Not in tension: one answer serves all three
Large data centers
Solar + long-duration storage
Full redundancy. The fastest, most scalable, cleanest and most cost-effective path.
  • Power in 12 to 16 months
  • ~$0.10/kWh firm now, ~$0.05 at terawatt scale
See the wave 3 site
Smaller, often modular
Flexible grid
Slot into available grid interconnections and bring their own capacity.
  • Grid assets, not liabilities
  • Batteries, community DERs, compute orchestration; not gas peakers
Terawatt scaleWin the AI raceBring communities alongBend the climate curve
Wave 3 · Off-grid, efficient and green · 1 GW AI data center · Esc to close
Sources: Solar Power World (Jan 22, 2026); LBNL (Jun 2026); G2 estimates. G2 cost analysis assumes thermal LDES.
The white paper

Want the full analysis?

Read the complete Terawatt Scale paper, with the data and sources behind every chart.

Read the full white paper ›
G2 Venture Partners · November 2026
Turn your phone sideways for the slides
G2 Venture Partners

TerawattScale

How to build AI data centers that work for industry, communities and the climate.

NOVEMBER 2026
Brook Porter, Jake Tauscher and Julia O’Donnell

A 1 GW AI data center powered by solar and long-duration storage
The pushback

Data centers are unpopular, and it showed in the midterms

1 · Data centers are unpopular

Americans who oppose a data center near their home

Aug ’2542%Feb ’2651%May ’2670%Aug ’2675%

strongly oppose   somewhat oppose

2 · The midterm results
56%of voters said it factored in
+7Senate seats flipped
TX · OH · GANew governors back a pause
43 of 44local limits passed
Seats that flipped
Senate: 7 seats flipped to Democrats, now 54–44KSIATXOHMENCSC Governors who back a pauseTXOHGANM

56% is the NBC exit poll (AI ranked 10th of 11 issues).

3 · Mapped to gigawatts
158.6 GW

of 383 GW planned (41%) sits where the new governor backs a pause.

Texas88.4Ohio21.9Georgia20.2New Mexico11.0Five others17.1

Of the rest: 18% new rules, no pause · 30% no governor race · 10% little signal.

Texas: who decides

Texas · 88.4 GW, more than half the exposed capacity

Governor-elect Gina Hinojosa (D) can only ask. Abbott’s appointees decide.

TCEQ
Environmental permits
DecidesAir and water permits, including on-site gas turbines, the route off-grid campuses use
Abbott picks3 of 3 commissioners
Hinojosa canAsk for a pause and name the chair; can’t fire commissioners
NowPermits frozen since Sep 21 until audits finish (~Dec 10)
PUCT
Utility commission
DecidesGrid rules, large-load hookups and who pays for grid upgrades
Abbott picks5 of 5 commissioners
Hinojosa canName the chair and send policy letters
NowRules Dec 17 on the next round of hookups (Batch Zero)
ERCOT
Grid operator
DecidesRuns the grid and the hookup queue
Abbott picksBoard, overseen by the PUCT
Hinojosa can1 of 3 board picks; can’t order denials
NowHookups paused since Aug 3 for an audit of ~300 projects
A binding pause needs a law. Republicans hold the state Senate 19–12; the session runs Jan 12 – May 31, 2027, and Hinojosa is sworn in Jan 19.
Sources
Sources: Heatmap News (Aug 19, 2026); Cleanview (Nov 4, 2026); Gallup (Oct 29, 2026); The Information tally of local measures (Nov 4, 2026); AP and CBS projections; Level39 on Texas permitting (Nov 4, 2026); Evercore ISI and Morgan Stanley (Nov 4, 2026; internal); G2 “Midterms and the AI Trade.” Results unofficial as of Nov 4, 2026.
Introduction

What industry needs, what communities deserve

Industry

What industry needs

  • Speed to power
  • Scale
  • Uptime
See the largest buildout in history

Data centers are already being built at a pace and scale unlike any infrastructure wave in history.

Manhattan Project$30BApollo Program$300BInterstate Highways$600BTelecom buildout ’96–’01~$1TAI buildout by 2030$5.2T◂ ~$1T already spent · 5x the telecom buildout

Infrastructure-wave spending as charted in the paper; AI buildout through 2030.

Communities

What communities deserve

  • Lower prices
  • No pollution
  • Tax revenue
See who is paying

This boom is being financed by the richest companies in history. Companies with these resources can afford to build well. There is no financial reason for a community to bear the cost of a data center.

AI platforms (5)~$18.4TOil majors (5)~$3.2THyperscaler capex, last 12 months$0.51TCapex, next 12 months (forecast)$0.90T

Market values Oct 2-5, 2026, and hyperscaler capex, as charted in the paper.

Sources
Introduction

Three waves of data center power

Wave 1 · Past

Grid connected

Build wherever you can plug in. Speed over everything.

Wave 2 · Today

Bring your own power

Gas turbines get sites online fast. Bandaid solution.

Wave 3 · Future

Scaled and sustainable

Two paths
Large data centersRenewables + LDES
Small to mid-sizedBring your own capacityGrid connected, flexible through storage
Wave 1 · 1 GW AI data center

Grid connected

Utility powerTransformersChillersCooling towersWater storageNetworking room
Wave 2 · Bring your own power · 1 of 5

Gas turbines and batteries on site

Close-up · what is new
Aeroderivative gas turbinesBESS
Wave 2 · 2 of 5

VAST storage

Close-up · what is new
Flash storage tier
Wave 2 · 3 of 5

Liquid cooling

Close-up · what is new
Liquid cooling: CDUs feed the racksTrim chillers, hottest hours only
Wave 2 · 4 of 5

Waste heat recovery

Close-up · what is new
Waste heat recovery
Wave 2 · 5 of 5

Autonomous construction

Close-up · what is new
Autonomous excavatorsAutonomous haul trucks
Wave 3 · Desert Southwest

Off-grid, efficient and green

SolarLong-duration thermal storageSolid-state transformersLiquid coolingBESS
Cheapest and most scalable

Renewables are the cheapest and most scalable form of power

Cheapest new electricity

Unsubsidized LCOE, $/MWh, 2025

Solar PV, utility$58Wind, onshore$61Gas combined cycle$78Geothermal$88Coal$122U.S. nuclear$180Gas peaking$200

Solar fell 84% in sixteen years, from $359 in 2009 to $58: from the most expensive source to the cheapest.

Still 5x gas after adjusting for capacity factor

Annual manufacturing capacity, GW, 2025

Gas turbines68 GWSolar modules, nameplate1,400 GWSolar, adjusted for capacity factor~350 GW~5xgas turbines, after the adjustment
Sources
Intermittency

Intermittent renewables cannot serve data centers alone, and firming with li-ion is too expensive

Up-front cost to firm a 1 GW AI campus with solar + Li-ion

~$5.8B97%~$9.5B99.4%~$32B est.99.999%Uptime
The missing piece: cost-effective long-duration (50–100 hours) storage
Sources
Sources: Ember, “24 Hour Solar Electricity” (June 2025): Ember’s solar and battery sizing for Las Vegas, priced at Ember’s 2024 global costs ($388/kW solar, $165/kWh storage, grid connection, inverter, 10% soft costs). Past 99.4% (dotted): G2 extrapolation of Ember’s sizing trend.
Commercializing

Long-duration energy storage is scaling now

Antora installationCommercial scale
Antora

Heated carbon blocks

Energy Dome installationCommercial scale
Energy Dome

Compressed carbon dioxide

Form Energy installationPilot scale
Form Energy

Iron-air batteries

Sources
Scorecard

Solar and LDES is the fastest, most scalable, and most cost effective option for data center builders

OptionSpeedScaleCost
Renewables + LDES

Why it leads

  • Speed: solar goes from groundbreaking to power in 12 to 16 months, the most impressive record of execution at speed today.
  • Scale: ~1,400 GW of solar modules a year, 5x gas even after discounting for intermittency; wind adds 165 GW globally.
  • Cost: ~$0.10/kWh firm now, with potential for ~$0.05/kWh at terawatt scale, which no other option can achieve.
  • Maturity: solar and wind with storage are among the four proven options; Antora and Energy Dome are at commercial scale.
Natural gas (BTM)

Where gas falls short

  • Speed: the table rates gas yellow (2 to 5 years); the text gives turbine lead times of five or more years.
  • Scale: 60-70 GW of turbines a year, ~100 GW by 2030; gas supply growth powers only ~10 GW of data centers annually.
  • Cost: comparable at ~$0.10/kWh firm over the medium term, but not on a cost curve like solar and storage.
  • Maturity: proven, one of the four options that rise above the rest; also the main source of pollution and noise communities fight.
Grid: giga-scale

Firm grid power at scale

  • Speed: slowest for large pockets of firm power; median 61 months from interconnection request for projects online in 2025.
  • That wait was 22 months in 2008 (LBNL, Queued Up 2026).
  • Scale: interconnection queues stretch five years or more; the grid has run out of firm, industrial scale power.
  • One operator told us firm power from the grid is infinitely expensive and unavailable.
  • Maturity: proven; we expect most behind-the-meter sites to connect eventually, build first, interconnect second.
Grid: medium-scale, flexible

Modest allocations, own capacity

  • Speed: operators are finding more modest grid allocations, particularly when the data center brings its own capacity; named in the speed verdict.
  • Scale: suits smaller, often modular, data centers slotting into available interconnections, not giga-scale sites.
  • Cost: comparable at ~$0.10/kWh firm; named in the cost verdict alongside solar and LDES.
  • Capacity options: compute flexibility, virtual power plants, on-site or near-site batteries; gas peakers are expensive, backlogged, hard to permit.
Geothermal

Years from gigawatt scale

  • Maturity: next-generation geothermal is being proven in the field now.
  • Scale: can supply power where the geology allows, but is years from gigawatt-scale deployment.
  • Belongs in the long-term mix; will not carry the next 100 GW.
Nuclear fission

First units at decade's end

  • Maturity: still being developed in its new small and advanced forms, with many shots on goal.
  • Speed: the first commercial units are expected around the end of the decade.
  • Belongs in the long-term mix; will not carry the next 100 GW.
Nuclear fusion

Not ready for this wave

  • Maturity: promising, but will not be ready for this wave.
  • Belongs in the long-term mix; will not carry the next 100 GW.
Wave power

No economical demonstration yet

  • Maturity: ocean or wave power has yet to demonstrate economical potential, even at demonstration scale.
  • Belongs in the long-term mix; will not carry the next 100 GW.
Orbital data centers

Compelling, with open questions

  • Space-based solar has compelling characteristics: no land use, modular scalability, cheap energy and cooling.
  • Near-term challenges: launch cost and launch capacity, although SpaceX is moving quickly.
  • Outstanding questions on orbital compute hardware; will not carry the next 100 GW.
< 2 yrs
> 100 GW/yr
$0.08-0.12 / kWh-firm
2-5 yrs
25-100 GW/yr
$0.12-0.16 / kWh-firm
5+ yrs
< 25 GW/yr
$0.16-0.20 / kWh-firm
Gray: too early to reliably estimate

Tap any option for why it scores that way.

Sources
Climate

This is also the best solution for the climate

US greenhouse gas emissions, Gt CO2e a year

56720052015202520356.5 Gt5.4 Gt~7 Gt: mostly gas4.8 Gt: clean buildout

Shaded: 2026 to 2035, G2 estimates.

Why the paths split

Twenty years of progress

  • The US cut emissions by about 1 Gt over 20 years; the power sector drove 80% of that (Rhodium Group, Jan 2026).
  • Major contributions came from the scaling of renewable energy.
  • That progress came in a world of stable power demand; that has now changed.

Current path, mostly gas

  • We estimate that on its current path, building mostly natural gas, the US reaches almost 7 Gt of emissions by 2035 (G2 estimate).
  • The climate needs power that does not lock in another thirty years of combustion.
  • How the US builds data centers over the next 10 years will be the single most significant determinant of our climate trajectory.

Clean buildout keeps emissions falling

  • Data centers built with clean technologies let the US keep dropping emissions while scaling clean energy and leading in AI (G2 estimate).
  • Solar backed by long-duration storage with full redundancy is also the cleanest and most cost-effective path.
  • Designed right, the firming reserve runs only a few hours a year, minimizing emissions.
Sources
Sources: Rhodium Group (Jan 13, 2026); G2 estimates. G2 estimates for the 2035 emissions paths, as charted in the paper.
Takeaway

Cost-effective power at speed and scale; climate and community friendly

IndustryFast, firm, abundant, cost-effective power
CommunitiesLower bills, clean air and water, lasting jobs and tax revenue
ClimateAvoiding another 30 years of combustion
Not in tension: one answer serves all three
Path 1 · Large data centers

Solar + long-duration storage

Full redundancy. The fastest, most scalable, cleanest and most cost-effective path.

  • Power in 12 to 16 months
  • ~$0.10/kWh firm now, ~$0.05 at terawatt scale
Path 2 · Smaller, often modular

Flexible grid

Slot into available grid interconnections and bring their own capacity.

  • Grid assets, not liabilities
  • Batteries, community DERs, compute orchestration; not gas peakers
Terawatt scaleWin the AI raceBring communities alongBend the climate curve
Sources
Sources: Solar Power World (Jan 22, 2026); LBNL (Jun 2026); G2 estimates. G2 cost analysis assumes thermal LDES.
The white paper

Want the full analysis?

Read the complete Terawatt Scale paper, with the data and sources behind every chart.

Read the full white paper ›